Locate Pile head with a pressure shovel |
Set the casing to check collapse. Backfill the surrounding of
of set casing with excavated earth. |
|
|
|
|
|
|
The drilling of the pile is done till the required depth is achieved, by combining air, water, cement fluid through special casing for pile extraction |
The pile is brought off the ground by attaching crane wire to specialized multiple pulley. After bringing the pile off, the cavity is filled with water and cement fluid mix. |
|
|
|
|
|
|
The upper part of the cut pile is held by medium size crane and lower part is held by multiple pulley or mount with reactive force.@Chose the wire depending on the weight of the pile. |
The pile is cut into safe lengths by using Oosumi dismantling machines. To check dust problem during cutting, water is sprayed through high washers. |
|
|
|
|
|
|
The cut pile is removed by medium size crane |
The cavity resulting from pile extraction is filled with cement fluid and sand mix. Please check the composition with the supervisor. |
|
|
|
|
|
|
The dismantled piles are cleared with the help of medium size cranes. Glass and steel are disposed separately |
|